Here are your 5 duties: Maintain Polarization, Maintain Cryogens, Move Target, Respond to Alarms, Log Everything.

 

 

           Set of slides with operational settings: QT_Operational_Settings.pdf


           The first thing (on the UVA-QT system) to check is the overall status of the system on QT-HMI, and the main part of the screen is the following.
           

           System status:  "ON"
           Both Liquefiers:  "Liquefy" mode (or could be either "Cooldown" or "Manual" mode depending on the current conditions different from "Liquefying").
           Purifier A:  "Manual" mode
           Purifier B:  N/A (we don't have a purifier B)
           HR3: "ON" + Green check mark.

           If you see "Alarm" on any of those status indicators (in the above picture), then that needs to be addressed/fixed soon.
           If that's the case, coordinate with the Target Expert on shift to fix the Alarm.

          

           The overview screen (example)
          
           

           This example picture illustrates that both Liquefiers are "ON". Liquefier A is in "Idle" mode, whereas Liquefier B is in "Liquefy" mode.
           ("Idle" mode means, the Liquefier is just holding liquid helium at ~4 K but not producing).
           Also, you can monitor the LHe, LN2 levels in the magnet, as well as the LN2 level in the purifier as well. Another example image is below.
           

          
           

           Check each Liquerfier screens (A & B) at least once per hour. A sample operational screen is below.
        
          
           
          
             The main components to check on the Liquefier screens are below:
             1) Mode (top left): Should be Run + Auto + Liquefy mode if it's in the production mode
             2) Cold head temperatures: Should be around > 3 Kelvin.
             3) Dewar level keeps increasing and does not do frequent large fluctuations between 0-275 Liters. If you start seeing large frequent fluctuations, then contact the Target Expert on shift immediately.
             4) Make sure FC501(A/B)I (actual inlet gHe flow) is close to FC501(A/B)Q  (gHe set-flow from PID)      (see "Settings" screen to check the set values)
             5) Make sure FC(A/B)I (actual outlet gHe flow) is close to FC(A/B)Q  (gHe outlet set-flow from PID)     (see "Settings" screen to check the set values)


In terms of the UVA-QT system maintenance, we need to keep the LN2 levels in the purifier always above 50% for higher production rate.

  Fill ProcedureProcedure
Filling LN2 to the purifier (remote: using the outside LN2 tank)https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10337
Filling LN2 to the purifier (in-person: using a portable LN2 Dewar)https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10053


 
                                  


 

Move Target

 

Before move:

 

 

Move Target Physically

 

 

Change NMR

 

There are 2 NMR coils, one in the Top cup, one in the Bottom.

 

 

Check Position

 

 

Alarms and Safety

 

 

Log Everything

 

In the Paper Logbook:

 

 

In the Hall A Log and Paper Logbook: