Here are your 5 duties: Maintain Polarization, Maintain Cryogens, Move Target, Respond to Alarms, Log Everything.

 

 

Next make sure all the necessary control screens are up. You should have PDP, the Cryo Controls, strip charts, and the alarm handler accessible.

Maintain Polarization

A good microwave frequency for the material will change as the material acquires dose.  Thus the target operator is required to pay constant attention to the time evolution of the polarization and the microwave frequency.

NMR 

 

Microwaves

User Interface of Microwave VIExample of Polarization vs Time



Maintain Cryogens

 

The cryogens are maintained by automatic PID loops. Your job is generally to monitor these loops and step in if they fail.

Nose Level

 

 

Magnet Liquid Level

 

QT System

           Set of slides with operational settings: QT_Operational_Settings.pdf


           The first thing (on the UVA-QT system) to check is the overall status of the system on QT-HMI, and the main part of the screen is the following.
           

           System status:  "ON"
           Both Liquefiers:  "Liquefy" mode (or could be either "Cooldown" or "Manual" mode depending on the current conditions different from "Liquefying").
           Purifier A:  "Manual" mode
           Purifier B:  N/A (we don't have a purifier B)
           HR3: "ON" + Green check mark.

           If you see "Alarm" on any of those status indicators (in the above picture), then that needs to be addressed/fixed soon.
           If that's the case, coordinate with the Target Expert on shift to fix those.

          

           The overview screen (example)
          
           

           This example picture illustrates that both Liquefiers are "ON". Liquefier A is in "Idle" mode, whereas Liquefier B is in "Liquefy" mode.
           ("Idle" mode means, the Liquefier is just holding liquid helium at ~4 K but not producing).
           Also, you can monitor the LHe, LN2 levels in the magnet, as well as the LN2 level in the purifier as well. Another example image is below.
           

          
           

           Check each Liquerfier screens (A & B) at least once per hour. A sample operational screen is below.
        
          
           
          
             The main components to check on the Liquefier screens are below:
             1) Mode (top left): Should be Run + Auto + Liquefy mode if it's in the production mode
             2) Cold head temperatures: Should be around > 3 Kelvin.
             3) Make sure the Liquefier is producing LHe and the Dewar level keeps increasing  (~4L/hr in average)
                  If you start seeing large frequent fluctuations (similar to the following image).
                  It may be an indication that the Dewar level sensor tubes are contaminated. Please contact the Target Expert on shift immediately.
                  Procedure for cleaning the tubes: https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10401
                 
             4) Make sure FC501(A/B)I (actual inlet gHe flow) is close to FC501(A/B)Q  (gHe set-flow from PID)      (see "Settings" screen to check the set values)
             5) Make sure FC(A/B)I (actual outlet gHe flow) is close to FC(A/B)Q  (gHe outlet set-flow from PID)     (see "Settings" screen to check the set values)


In terms of the UVA-QT system maintenance, we need to keep the LN2 levels in the purifier always above 50% for higher production rate.

  Fill ProcedureProcedure
Filling LN2 to the purifier (remote: using the outside LN2 tank)https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10337
Filling LN2 to the purifier (in-person: using a portable LN2 Dewar)https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10053




 
                          

Cryo Control Panel (CCP)

It is a LabVIEW program (VI) that controls and monitors all cryogenic devices (except the QT Liquefier System).  It is running on the target computer.

The target operator

Main Panel of CCP

Move Target

The position of target cells is controlled by moving the target stick via the Target Lifter VI on the target computer.  The run coordinator schedules the next target move.

The target operator moves the target at the scheduled time, by following the instructions below.  If the Target Lifter VI shows any error or causes any unexpected condition, please call the target expert.

User Interface of Target Lifter VI

Change NMR

 

There are 2 NMR coils, one in the Top cup, one in the Bottom.

 

 

Check Position

 

 

Respond to Alarms

The target operator responds to all alarms that appear on the QT HMI, the Cryo Control Panel, the Microwave VI, the Target Lifter VI and the PDP.  There are two levels of alarms;

An instruction on each alarm can be found in the documentation on the corresponding subsystem page.  Call the target expert if you cannot find it. 

Log Everything

After filling the LN2 (liquid Nitrogen) in the purifier, the magnet shield, the LHe (liquid helium) to the Magnet space, and the fridge space should be recorded on the FNAL elog (https://dbweb8.fnal.gov:8443/ECL/spin_quest/U/login). Each filling should be recorded on the FNAL ECL by creating a new Entry under the Target category and followed by approved procedures. Some target-related elogs pattern is listed below:

Entry Subject: Filled the purifier using LN2 outside tank

I filled the purifier using the LN2 outside tank, following the procedure on docdb #10337 (by Jordan Bohn).
LN2 Tank level = 37 inwc 
LN2 Purifier = Starting time=15:38, Starting level=63.0%, Finish time=15:59, Finish Level=91.0%

In the above Elog, the Purifier is filled with LN2 using the approved procedure using the outside LN2 tank. Before filling the purifier, look at the LN2 tank manual gauge. For filling the purifier, the LN2 tank should be above 10 inwc. These instructions are listed on the procedure on docdb #10337. 

Entry Subject: Filled the magnet shield using LN2 outside tank

I filled the magnet shield using the LN2 outside tank, following the procedure on docdb #10337 (by Jordan Bohn).
LN2 Tank level = 30 inwc 
LN2 Magnet shield= Starting time=16:38, Starting level=55%, Finish time=17:00, Finish Level=91.0%

In the above Elog, the magnet shield is filled with LN2 using the approved procedure using the outside LN2 tank. Before filling the magnet shield, look at the LN2 tank manual gauge. For filling the magnet shield, the LN2 tank should be above 10 inwc. These instructions are listed on the procedure on docdb #10337. 

Entry Subject: Filled the target fridge with LHe

I filled the target fridge with LHe
* From nose level = 0% at 15:01
* To Heat-Ex Top at 16:13.

Before filling the fridge space with LHe, we do not need to manually open the gate valve bypass valve because we are working on the remote gate valve bypass valve. We will swap out the manual gate-valve bypass valve with a remote gate valve. The approved procedure is on DocDB# 10375.  

Entry Subject: Fill the magnet with LHe using QT Dewar

We filled the magnet up to 45% (145 L) with LHe using QT Dewar B and maintained the coils' temperature at 4.4K.
Today's transfer efficiency was 65%.

In the above FNAL elog, the choice of the QT Dewar A/B and how to calculate the transfer efficiency are listed on the procedure on docdb #9670.  



Add to FNAL elog: