Counting House Connections

  • pass all cables in




Long Term List:





Most Critical (before shielding):
Drill holes for uni-strut mount (FNAL:  day)
Move actuator frame into place (FNAL+UVA:1 day)
Install gate valve (FNAL+UVA:1 day)
Connect roots piping (UVA:3 days)
Re-tune positioning (FNAL+UVA:3 day)
leak checking (UVA:7 days)
open shell placement of target insert (UVA:1 day)
open-cold survey (UVA:1 day)
Roots ORC prep + ORC (FNAL+UVA:4 days)
Install CM-platforms and beamline piping (FNAL+UVA:4 days)
make and install all tubing/piping for target connections (UVA:14 days)
Install all cave tubing/piping (UVA: 5 days)
finish out of cave piping (FNAL:14 days )
Lay all piping and wiring in west penetration: (FNAL+UVA: 14 days)
Magnet power (two 14 mm cables) (66 ft from magnet to magnet power-supply
on cryo-platform)
Internal magnet sensors
External magent sensors TC lines (sixteen 1 mm cables) (highly length
sensitive)
LHe level probe (one 7 mm cable)
LN2 level probe (one 7 mm cable)
Shim power (two 7 mm cable)


Second Critical (after shielding):
Installation of shell\nose\turret\fridge (UVA: 3 days)
Installation of actuator table (UVA: 3 days)
ORC for target actuator prep (UVA: 14 days)
Custom electronics ORC prep (UVA: 14 days)
All front running electrical connections:(FNAL+UVA: 7 days)
microwave PS and controls
pressure sensors
He3 pressure probe
interlocks


Third Critical (supporting systems):
finalize vacuum piping (UVA: 7 days)
pneumatic valves (FNAL+UVA: 3 days)
leak checking (UVA:7 days)
Install microwave water and chiller (UVA: 3 days)
Install microwave system(UVA: 3 days)
NMR setup and connection through east penetration(UVA + LANL: 4 days)