Useful information
P&IDs
P504 HR3 P&ID 20191209 SSG.pdf
P504 P&ID (AO) Feb 26, 2020 -reprint.pdf
1) Open V9a and V21a from PLC
2) keep V30 hand valve closed
3) Keep BV02 & RegX hand valves (going to/from liq A, B) closed
4) Open SV01 and SV03 (Note: if the valves are not opening via PLC, then check whether the system is in Manual + Run mode, if not select that mode to open SV01 and SV03)
5) Pump down using the setup that we just installed on the Vent.
6) Opening hand valve V30 slowly increases the pump sound (takes a couple of seconds to respond due to the long path to reach the pump)
See the above picture in step 2