The top mounting plate can be positioned whenever the techs come to do it. 
The machining and materials from UVA have arrived and are ready.  This
includes the bottom target tri-winged frame and the new aluminum feet
holders.  The threaded feet are also finished from FNAL.  The dowel pins
should be done soon.  After this the lifter frame should go in and then
the magnet can in principle go into position.  In order for us to be ready
for that we want new PTFE seals which are more radiation resistant.  We
need to clean and prep the magnet and can, and to do the doc survey.
1.) Survey on doc with full system open (no nose, no nitrogen shield, no
beam windows).  Survey the magnet aperture, the target insert along X
only, and the outside fiducials (can and top flange).  The primary goal of
this survey is to generate fiducials on the can and top flange to help
align when going into position in the cave.
Do ImmediatelyAdditional Information

Fridge sensors

1KOhm Ruthenium Oxide
Determine and measure true path for all cables coming from target cave

Front Penetration → Racks on Cryo platform → Counting House

Side Penetration → Racks on Cryo platform → Counting House
Liquid Helium Level Probe mounting clipsBeing made at UVa - 7/17/19
Replace Black BUNA-N O-rings

Measure existing O-rings and find PTFE (Teflon) equivalents

  • Run/bypass valves
  • Shell to magnet
  • Shell to turret
  • Turret to fridge
  • Electrical feedthroughs
  • Bottom can
  • Red pop-off valve
Make and test indium seal on shell/nose 
  
Buy a flaring tool for copper tubing 
Assemble and test microwave system

Needs to be shipped from UVa - 7/17/19

Borrow gore cable from UVa

Need waveguide too

Get Liverpool NMR Q-meter (and ancillary equipment) from LANL 
Once EIO arrives, connect EIP and test air core cable 
Setup sensors on stickCheck with lakeshore
Stink test in the target loading areawith "special" spray
Setup and test manometer 
Setup external magnet sensors 
Shim Microwave actuator bushings for hard stop and top target 
Things to do when not working on the immediate thingsAdditional Information
  
Setup Target Rack

Stepper motor drives and power supplies

ADC for position readbacks

Microwave EIP

Lakeshore 218 x2

Level Probe Readout

Turbo readout and Controller

IV gauge readout

Teledyne Hastings readout

4He & 3He manometers

Possibly Microwave Power Supply

Target Insert Lakeshore

Fridge Lakeshore

External Magnet Lakeshore

 

Get hoses for microwave (EIO)Either hard plastic or rubber
Target Controls ComputerJosh will find it
All cabling from target to racks and counting houseneed lengths and to order cables
setup target operator station 
setup target loading station 
Finalize NMRtesting still needed
Target handler and alarm system 
Setup NMR VI 
Annealing controls 
Setup and test Main Gate Valve 
Test Air-core cable with EIP/microwave 
Setup Insert and leak check and electronics check, sensors, coils, SMA 
Setup Nuc and oscilloscope and PDP 
Setup Roots stack controller and power 
Get some plastic tubs and foam dewars 