IMG_0254.jpg

  1. HR3 Manual
  2. HMI Interface and Connectivity Manual
  3. Liquefiers (A B) Manual
  4. Purifier Manual
  5. QT System P&ID Information
  6. Coldhead Compressors Manual
  7. HMI Cabinet Manual
  8. Pneumatic Air Supply Manual

Operational Configuration (←Click)

Routine Maintenance Procedures


General/Other Procedures

PurposeInstructions/Links
System Startup Procedure

QT System Starting Procedure

Cooldown

Look At Updated Page

For planned power outage

Shut Down and Restart Procedures

Taking purity measurements at various places in the system

Measuring gHe purity


Troubleshoots

IssueReasonWhat to do?
If the Dewar level indicators have large fluctuationsLevel sensor tubes are contaminatedFixing dewar level indicator
FNAL Approved procedure: https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10401
Coldheads blocking alarmPossible contamination
or cold heads have been running so long without any intake gHe for a while
  1. Resolving Liquefier Blocking Alarm when Liquefier is on Liquefy Mode
  2. Resolving Liquefier Blocking Alarm when Liquefier is on Idle Mode






Useful Information

  1. The volume of an outside gHe tank: 1600 cubic feet (V = 45306.95 L)
  2. 100 slm rate on Magnet FC is equivalent to ~ 192 LHe liters per day (i.e. assuming both LQ A and B are running)

Useful Contact Information


  1. Cryofab : https://www.cryofab.com/contact
    Call +1 (800) 426-2186 and ask for extension #14 (Mr. Tam)
    Tell this serial number and he will recognize us
    Image